CONSULTANCY
PROJECTS
1. Checking &
Rectification of Dynamic Imbalance of the Rotor Part of 22 kW Motor of Indane Bottling Plant (Indian Oil Corporation
Limited, Assam Oil Division), North Guwahati, Guwahati.
Period
& Amount (in Rs lakhs) :
One year (Feb. 2004-Dec. 2005), (0.05)
(Completed)
Funding agency: Indian Oil Corporation,
Guwahati.
Status: Principal Consultant
Institution: Indian Institute of Technology Guwahati
2.
Consultancy and Technical Design of the Deep Groove Ball and Cylindrical Roller
Bearings for high-speed applications.
Period & Amount (in Rs lakhs) :
One year (Feb. 2004-Dec. 2005), (8.74)
(Completed)
Funding agency: DRDO, New Delhi.
Status: Principal Consultant
Institution: Indian Institute of Technology Guwahati
3. Experimental
Estimation of Dynamic Coefficients of Annular Seals for Turbopumps.
Period & Amount (in Rs lakhs): (October 2004 -
June 2007), (3.75)
(Completed)
Funding agency: LPSC, ISRO, Trivendrum
Status: Principal Consultant
Institution: Indian Institute of Technology Guwahati
4. Design and Development of First Generation Tapered
Roller Bearings.
Period & Amount (in Rs lakhs): (April 2006 - June
2007), (7.55)
(Completed)
Funding agency: Tata Bearings, Kharagpur
Status: Principal Consultant
Institution: Indian Institute of Technology Guwahati
5. Consultancy and Technical Design of the Angular
Contact (Split type) Ball Bearings for High-Speed Applications.
Period & Amount (in Rs lakhs): One year and four
months (Jan. 2007- Dec. 2008), (9.73)
(Completed)
Funding agency: DRDO, New Delhi.
Status: Principal Consultant
Institution: Indian Institute of Technology Guwahati
6. Consultancy on the Investigation of the Vibration
Problems of the Primary Limestone Crusher Unit of the M/S. Lafarge Umiam Minining Private Limited, Shella, Meghalaya.
Period & Amount (in Rs lakhs): One month (April
2007) (2.87)
(Completed)
Funding agency: Lafarge Umiam Minining Private Limited, Shella,
Meghalaya
Status: Principal Consultant
Institution: Indian Institute of Technology Guwahati
7. Consultancy on design and development of test stand
for dynamic characterization of fluid film bearings and labyrinth seals.
Agency: Skoda
Power, Plzen, Czech. (Completed/unregistered)
8. Consultancy on the Investigation of the Vibration
Problems of the Conveyor Belt Gallery of the M/S. Lafarge Umiam
Minining Private Limited, Shella,
Meghalaya.
Period & Amount (in Rs lakhs): One month (March
2009), (1.5)
(Completed)
Funding agency: Lafarge Umiam Minining Private Limited, Shella,
Meghalaya
Status: Principal Consultant
Institution: Indian Institute of Technology Guwahati
9. Consultancy & Technical Investigation of the
Vibration Resonance Problems in Conveyor Belt Galleries of the M/S. Lafarge Umiam Minining Private Limited, Shella, Meghalaya.
Period & Amount (in Rs lakhs): Two months (June
2009 - July 2009), (2.42) (Completed)
Funding agency: Lafarge Umiam Minining Private Limited, Shella,
Meghalaya
Status: Principal Consultant
Institution: Indian Institute of Technology Guwahati
10. Consultancy and Technical Design of Tapered Roller
Bearings.
Period & Amount (in Rs lakhs): One year and six
months (Oct. 2010 – March 2012), (14.1) (Completed)
Funding agency: DRDO, New Delhi.
Status: Principal Consultant
Institution: Indian Institute of Technology Guwahati
11. Root-cause Investigation & Rectification of an Industrial Fan
Assembly Failure.
Period
& Amount (in Rs lakhs): Two months (July-August
2013) (0.24) (Completed)
Funding
agency: Radiant Manufacturing Pvt. Ltd. (Distillery Division), Khatkahti, Assam.
Status:
Principal Consultant
Institution:
Indian Institute of Technology Guwahati
12. Vibrational
Site Survey for Magnetic Resonance Imaging (MRI)
Installation
Period & Amount
(in Rs lakhs): One month (July 2017) (0.30) (Completed)
Funding
agency: GE Healthcare, New Delhi (Nemcare Hospital,
Guwahati).
Status:
Principal Consultant
Institution:
Indian Institute of Technology Guwahati